Your Pool Construction Journey – From Plan to Plunge

Your Pool Construction Journey

From Plan to Plunge: What to Expect at Every Stage

Building a swimming pool is one of the most exciting upgrades you can make to your home. Understanding the process is the key to a stress-free and enjoyable experience. This guide walks you through every step so you know exactly what to expect.

Remember, the very first step to a successful build is a professional plan. Your plan is the blueprint that guides every stage listed below.

A Note on Timelines: Typical gunite pool projects take 8–14 weeks from excavation to first swim. Timelines can vary based on location, project complexity, weather, and municipal inspections.

The Construction Process: A Step-by-Step Guide

Phase 1: Pre-Construction

Step 1: Design & Permitting

What Happens: Finalize your pool design and submit to your local building department for approval to meet all safety and construction codes.

Typical Duration: 2–8 weeks (varies by municipality)

Phase 2: The Heavy Lifting

Step 2: Layout & Staking

What Happens: Your builder paints and stakes the pool shape and position. First chance to see the true scale of your pool.

Typical Duration: 1 day

Step 3: Excavation (The Big Dig)

What Happens: Heavy machinery digs the precise pool shape and depth. Transformative and exciting!

Typical Duration: 1–2 days

Step 4: Steel Reinforcement

What Happens: Rebar is installed to create the pool’s structural integrity.

Typical Duration: 1–2 days

Step 5: Plumbing & Electrical Rough-In

What Happens: Pipes, drains, skimmers, lighting, and other systems installed before concrete.

Typical Duration: 2–4 days

Step 6: Gunite / Shotcrete (Forming the Shell)

What Happens: High-strength concrete sprayed over steel to form pool shell, then cured.

Typical Duration: 1 day to apply, 7+ days to cure

Phase 3: The Finishing Touches

Step 7: Tile & Coping

What Happens: Decorative waterline tile and coping installed.

Typical Duration: 2–5 days

Step 8: Decking & Patio Installation

What Happens: Surrounding deck area formed and poured or laid.

Typical Duration: 2–7 days

Step 9: Pool Equipment Setup

What Happens: Pump, filter, heater, and sanitizing systems installed and connected.

Typical Duration: 1–2 days

Step 10: Plaster / Interior Finish

What Happens: Waterproof interior finish applied, giving the pool its final color and feel.

Typical Duration: 1 day

Phase 4: The Finish Line

Step 11: Filling the Pool & Chemical Start-Up

What Happens: Pool is filled, equipment started, and water chemistry balanced for the first time.

Typical Duration: 2–3 days

Step 12: "Pool School" & Handover

What Happens: Builder walks you through pool operation, equipment usage, and maintenance. Time to grab your swimsuit!